2015

Flensburg, Germany – The assembly of gas-fired boiler of the thermal power of 75 MW and electrical power of 65MW. The scope of deliveries included the assembly of the pressure part of the boiler,

2014

Annweiler, Germany – The repair of the steam boiler of the capacity of 65 t/h, at the Kartonfabrik Buchmann plant. The scope of deliveries included the replacement of superheater coils, economizer coils, boiler membrane walls, combustion system and fresh air system

Sisseln, Switzerland – The assembly of gas-fired steam boiler of the capacity of 15 t/h at the DSM Sisseln Terra Plant. The scope of deliveries – the assembly of the pressure part, combustion system, gas and oil burners, airflow ducts, flues and technological piping

Antwerp, Belgium – The assembly of two gas-fired steam boilers of the capacity of 70.3 t/h each at the Bayer Antwerpen Plant. The scope of deliveries – the assembly of the pressure part, combustion system, gas burners, airflow ducts, flues and a stack.

Vienna, Austria – The assembly of two gas-fired water heaters of total power of 170 MW at the Fernwarme Wien Plant. The scope of deliveries – the assembly of the pressure part, combustion system, gas and oil burners, airflow ducts and flues. The weight of pressure elements 575 tons, the weight of airflow ducts and flues 120 tons.

Rest – around 30 short-term contracts – repairs, modernization, on the premises of plants in Germany, Poland and France

2013

Rest – around 10 short-term contracts – repairs, modernization, on the premises of plants in Germany